was unfinished, the engineer had no lawful authority to termi nate the contract, because the fault in the delay was in the government and its officers.

2. That conceding the authority to terminate the contract was lawfully exercised, the consequence was that when the work was done by the government, or by other contractors at its instance, such work was done at his risk of loss or of profit, and if, when finished, it cost the United States more than it would if done under his contract, he was responsible for the loss, and if done for less, the gain was his.

We cannot concur in this latter proposition.

It seems very doubtful if, in the event of the termination of his contract under the clause authorizing the engineer to do so, the contractor is liable to the United States for any thing beyond the ten per cent retained. This ten per cent is retained, in the language of the contract, until the whole shall be completed. It is retained as security for that end. The work is to be completed by others, and the expenses deducted from any money that may be due him. He is to be responsible for damages caused to others by the delay. If, therefore, he is responsible to the United States beyond the sum due him at the time the contract is taken from him, it is not by the express terms of the contract, but on the general doctrine of damages on failure to fulfil any contract.

So, on the other hand, we think it equally clear that when his contract is rightfully terminated, he is entitled to no further rights in regard to its performance by others. The government does not, by reason of being compelled by his failures to resume control of the work, do so for his benefit, but for its own. They do not thus become his agents to do the work for him which he failed to do, and let him reap the profits of a work which he refused or neglected to perform.

Nor are we able to see that the contract was wrongfully taken from him.

It may very well be contended that the engineer in charge is by the agreement of the parties made the judge of the exist ence of "such delay or inability to proceed with the work in accordance with the contract" as justifies him in taking it away, and that his action in that regard is conclusive. But the

counsel for the United States have not assumed that ground here, and it is not necessary to the decision of the case.

It may be safely asserted, however, that it will be presumed that his action was well founded until it is impeached by satisfactory evidence, and especially where, as in this case, the time limited for the completion of the work had passed. Such evidence is wanting in this case. It is true that there was some delay in the autumn of 1867 on the part of the engineers in locating the precise point where the rock was to be excavated and in determining the low-water mark with reference to which all the work was to be done, and this was not perfected until February, 1868. But there is no evidence that Quinn demanded that this should be done sooner, or that he desired to commence his work earlier.

There is satisfactory evidence that his delay was caused mainly, if not solely, by his inability to procure the nitroglycerine which, under his plan of working, was the only explosive that he could use. He had the entire work honeycombed with cells drilled for the reception of this explosive in due time, and if he could have procured it, would have completed the work in time, or at least his contract would not have been taken away. The excuse is that the party who had contracted to deliver the nitro-glycerine failed in business and failed to deliver. But the authority of the engineer to terminate the contract did not depend on the value of excuses or the difficulty of performance. He had "full right and authority" to do this for inability to proceed with the work according to the contract, as well as for delay.

There was both delay and inability in this case, and we do not see that they were due to any failure on the part of the government.

In this connection it is said that Quinn should receive pay for the holes drilled for reception of the explosive in that part of the work not completed when it was taken from him. But the finding of the Court of Claims is that this was not used by the government or by the subsequent contractor, because the latter used gunpowder, which could not be profitably exploded in the holes drilled for the nitro-glycerine.

We think that the Court of Claims was right in reject

[blocks in formation]

ing the two first items of the claim as we have mentioned them.

But it is otherwise with regard to the ten per cent of the price of the work completed, retained by the government.

We have already seen that this was retained for the purpose of securing the completion of the work, and that if not completed by the contractor it was to be used in paying the expenses of such completion. In our view, it is a fair construction. of this part of the agreement that the money retained under it is for security that the contractor will not abandon his work, but will proceed in it with due vigor, and for indemnity to the United States in case he fails to do this. Unless, therefore, the government has sustained some loss, some pecuniary or legal damage by his failure, the money which he has fairly earned should be paid to him when the work which he agreed to do has been completed, though by others. In the case before us the United States made a clear gain of $33,000 by taking away his contract and making a new and more advantageous one with another person. Under such circumstances, the United States no longer has a right to the money withheld for indemnity and security, because the risk is over, the event has occurred, and instead of loss or damage there has been a gain by the transaction.

The judgment of the Court of Claims dismissing the petition will therefore be reversed, and the case remanded to that court with directions to render a judgment for claimant for the sum of $1,740; and it is

So ordered.

UNITED STATES v. AMES.

1. A bond accepted by the court upon ordering the delivery to the claimant of property seized in admiralty, is in the subsequent proceedings a substitute for the property; and the question whether a case is made for the recall of the property must be determined before a final decree on the bond is rendered in the District Court, or in the Circuit Court on appeal. Action on that question cannot be reviewed here.

2. A decree rendered on such a bond given with sureties by the claimant at the request and for the benefit of his firm, to which the property so delivered to him belonged, bars a suit against the other partners.

3. The fact that the adverse party had no knowledge touching the ownership of the property, and that, by reason of the insolvency of the defendants, payment of the decree cannot be enforced, affords, in the absence of fraud, misrepresentation, or mistake, no ground for relief in equity.

4. Conclusions of law are not admitted by a demurrer.

APPEAL from the Circuit Court of the United States for the District of Massachusetts.

The facts are stated in the opinion of the court.

Mr. E. S. Mansfield and Mr. G. A. Somerby for the appellant.

Mr. George O. Shattuck and Mr. Oliver W. Holmes, Jr.,

contra.

MR. JUSTICE CLIFFORD delivered the opinion of the court. Judicial cognizance of prize cases is derived from that article of the Constitution which ordains that the judicial power shall extend to all cases of admiralty and maritime jurisdiction; and the district courts for many years exercised jurisdiction in such cases without any other authority from Congress than what was conferred by the ninth section of the Judiciary Act, which gave those courts exclusive original cognizance of all civil causes of admiralty and maritime jurisdiction, including the seizures therein mentioned, the rule adopted being that prize jurisdiction was involved in the general delegation of admiralty and maritime cognizance, as conferred by the language of that section. Glass v. The Betsey, 3 Dall. 6; The Admiral, 3 Wall. 603; Jennings v. Carson, 1 Pet. Adm. 7; 1 Kent, Com. (12th ed.) 355; 2 Stat. 781, sect. 6.

Admiralty courts proceed according to the principles, rules,

and usages which belong to the admiralty as contradistinguished from the courts of common law. Manro v. Almeida, 10 Wheat. 473; 1 Stat. 276.

Seizure of the property and the usual notice precede the appearance of the claimant; but when those steps are taken, the owner or his agent, if he desires to defend the suit, must enter his appearance in the case, and the court may, in its discretion, require the party proposing to appear and defend the suit to give security for costs as a preliminary condition to the granting of such leave.

Due appearance having been entered, the claimant, if he wishes to avoid the inconvenience and expense of having the property detained until the termination of the suit, may apply to the court at any time to have the property released on giving bond, which application it is competent for the court to grant or refuse.

Bail in such a case is a pledge or substitute for the property as regards all claims that may be made against it by the promoter of the suit. It is to be considered as a security, not for the amount of the claim, but simply for the value of the property arrested, to the extent of the claim and costs of suit, if any, beyond the preliminary stipulation. Williams & Bruce, Prac. 210.

Whenever a stipulation is taken in the admiralty for the property subjected to legal process and condemnation, the stipulation is deemed a mere substitute for the thing itself, and the stipulators are held liable to the exercise of all those authorities on the part of the court which the tribunal could properly exercise if the thing itself were still in the custody of the court. The Palmyra, 12 Wheat. 1; The Wanata, 95 U. S. 611; The Steamer Webb, 14 Wall. 406.

Fees and expenses of keeping the property having been paid, it is the duty of the marshal to surrender the property as directed in the order of release; and it is settled law that if any one, in defiance of the order, unlawfully detains the same he is liable to be proceeded against by attachThe Towan, 8 Jurist, 223; The Tritonia, 5 Notes of

ment.

Cases, 111.
Concisely stated, the material facts as derived from the