... completion and acceptance of the whole work . The work was not completed at the specified time , chiefly in consequence of the failure of a third party to deliver to A. the necessary explosive , and the officer in charge terminated the ...
... completion and acceptance of the whole work . The work was not completed at the specified time , chiefly in consequence of the failure of a third party to deliver to A. the necessary explosive , and the officer in charge terminated the ...
Страница 31
... completed and accepted . Quinn having failed to complete the work by the 1st of October , it was taken from him on the 9th of November , 1868 , and , after advertising , let to other parties . For all the work completed he was paid at ...
... completed and accepted . Quinn having failed to complete the work by the 1st of October , it was taken from him on the 9th of November , 1868 , and , after advertising , let to other parties . For all the work completed he was paid at ...
Страница 32
... completed . It is retained as security for that end . The work is to be completed by others , and the expenses deducted from any money that may be due him . He is to be responsible for damages caused to others by the delay . If ...
... completed . It is retained as security for that end . The work is to be completed by others , and the expenses deducted from any money that may be due him . He is to be responsible for damages caused to others by the delay . If ...
Страница 33
... completion of the work had passed . Such evi- dence is wanting in this case . It is true that there was some delay in the ... completed when it was taken from him . But the finding of the Court of Claims is that this was not used by the ...
... completion of the work had passed . Such evi- dence is wanting in this case . It is true that there was some delay in the ... completed when it was taken from him . But the finding of the Court of Claims is that this was not used by the ...
Страница 34
... completed , retained by the government . We have already seen that this was retained for the purpose of securing the completion of the work , and that if not com- pleted by the contractor it was to be used in paying the ex- penses of ...
... completed , retained by the government . We have already seen that this was retained for the purpose of securing the completion of the work , and that if not com- pleted by the contractor it was to be used in paying the ex- penses of ...
Друга издања - Прикажи све
Чести термини и фразе
act of Congress action adverse possession affirmed alleged amendment amount appeal applied authority bank bill bonds Cañon Cañon City Central Pacific Railroad charter Circuit Court collector commissioners complainants Constitution construction contract corporation coupons court of equity creditors debt decree defendant delivered the opinion Denver Pacific Railway District Court duty earnings entitled equity evidence executed facts filed Fort Scott granted held interest issued judgment July jurisdiction jury JUSTICE Kansas Pacific Railway lands legislative legislature liable lien ment mortgage owner Pacific Railroad Company paid pany parties partnership payable payment person petition plaintiff in error possession proceedings purchaser purpose question railroad and telegraph received rendered road sect sold Stat statute suit supra Supreme Court taxation telegraph line thereof tion town town of Weyauwega township Treasury trustee Union Pacific Railroad United