94 C. Cls. CONTRACTS-Continued. - would encounter in the site which it contracted to it had expected. James Stewart & Co., 95. either misrepresentation or concealment on the part of defendant. Id. the United States, to deliver top soil to several parks Reediger, Inc., 120. parties and vested in the Government the right to the terms of the contract. Id. adduced to have been authorized and were made quantum meruit. Id. agreed price, for use in heating a post office; and where thereupon the Government refused to pay for 94 C. Cls. CONTRACTS–Continued. said coal on the ground that vendor had been "paid Belcher, 137. that the defendant did not by any act, conduct or Construction Co., 175. reasonably and within the provisions of the contract in tract. Id. damages the contracting officer denied all claims except to recover only the sum allowed by said decisions. Id. struction of an extension to the then existing heating Contracting Company, 244. or in the time for performance which resulted in any board, and plaintiff is not entitled to recover. Id. account of an alleged underpayment by plaintiff of its 94 C. Cls. CONTRACTS—Continued. to prove that it had complied with the provisions of the Id. by the evidence, it is held that plaintiff is not entitled Id. December 27, 1933, for the construction of certain of delay. Jacob Schlesinger, Inc., 289. the terms of the contract was final, submitted to his superior. Id. erroneous. Id. termaster General, denied plaintiff's request to work 94 C. Cls. CONTRACTS_Continued. States, 86 C. Cls. 461, it is held that plaintiff is entitled Inc., 356. is entitled to recover for extra costs and expenses on sible. Id. corporation engaged in slaughtering livestock and pre- & Co., 490. were physically present in plaintiff's yards did not constitute delivery. Id. full authority to incur the expenses in question and Corporation. Id. ation provided that the contractor was required to 94 C. Cls. CONTRACTS—Continued. to recover for storage on said quantities, respectively, 1935, to July 2, 1935. Id. the specifications to visit the site of the proposed 503. own negligence in not examining the site has failed to 89 C. Cls. 226, 250 cited. Id. contracts calling for erection and installation by of the contracts. Hirsch, 602. of delay and extensions of time after the contracts to do so was gross error. Id. tiff did not employ qualified laborers and efficient |