... specifications , schedules , and drawings , made part of the contract ; and where the speci- fications stated that the contour of the channel was improved to 21 feet depth and 400 feet width in 1913-1915 , and that mate- rial to be ...
... specifications , schedules , and drawings , made part of the contract ; and where the speci- fications stated that the contour of the channel was improved to 21 feet depth and 400 feet width in 1913-1915 , and that mate- rial to be ...
Страница 2
... specifications , schedules , and drawings , made part of the contract , the work to be com- pleted within a time ... specifications was 570.8 feet , being the height above mean tide in New York Harbor . As to contour of the channel the ...
... specifications , schedules , and drawings , made part of the contract , the work to be com- pleted within a time ... specifications was 570.8 feet , being the height above mean tide in New York Harbor . As to contour of the channel the ...
Страница 3
... specifications also provided that the plant should be of sufficient size to meet the requirements of the work , subject to the approval of the contracting officer . The contracting officer for the United States was D. McCoach , Jr ...
... specifications also provided that the plant should be of sufficient size to meet the requirements of the work , subject to the approval of the contracting officer . The contracting officer for the United States was D. McCoach , Jr ...
Страница 6
... specifications state very clearly that all of the channel under our contract had been dredged to 21 feet below datum and the in- tent of this contract was for the reestablishment of this depth . We naturally accepted this information ...
... specifications state very clearly that all of the channel under our contract had been dredged to 21 feet below datum and the in- tent of this contract was for the reestablishment of this depth . We naturally accepted this information ...
Страница 7
... specifications of the United States Engineers for dredging Maumee River and Bay Channel , Lake Erie , copy of which is attached hereto and made a part hereof , for the sum of Twenty- Two Cents ( $ 0.22 ) per cubic yard , place ...
... specifications of the United States Engineers for dredging Maumee River and Bay Channel , Lake Erie , copy of which is attached hereto and made a part hereof , for the sum of Twenty- Two Cents ( $ 0.22 ) per cubic yard , place ...
Друга издања - Прикажи све
Чести термини и фразе
additional agreement Albyn alleged amended amount approved April Article assets August bank bars bonds cartridge channel charges Chickasaw Choctaw Nation claim for refund Commissioner Company Congress construction contracting officer contractor Corporation cost Court 94 cubic yards damages December decision deduction defendant defendant's delay dredging entitled to recover Executive Order expenses Farm Board February February 15 feet follows furnished gold Government grain Haven Harbor held income Indian interest January January 17 Judge July June June 25 labor lands letter license liquidated liquidated damages loan Marc Klaw March March 15 material ment Missouri River natural gasoline November October operations oysters paid patent payment period Perth Amboy petition plaintiff Public Works Office received referred Reporter's Statement reservation Revenue Act River Settlor special findings specifications Stat statute Steel and Tubes thereof tiff tion tract Trade Board treaty trust United vessels War Trade Board wheat
Популарни одломци
Страница 340 - When private individuals of one nation spread themselves through another, as business or caprice may direct, mingling indiscriminately with the inhabitants of that other, or when merchant vessels enter for the purposes of trade, it would be obviously inconvenient and dangerous to society, and would subject the laws to continual infraction, and the Government to degradation, if such individuals or merchants did not owe temporary and local allegiance, and were not amenable to the jurisdiction of the...
Страница 281 - ... the Government may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been a failure to pay said required wages and to prosecute the work to completion by contract or otherwise, and the contractor and his sureties shall be liable to the Government for any excess costs occasioned the Government thereby.
Страница 449 - States, is or shall be admitted to any share or part of this contract, or to any benefit that may arise therefrom, but this article shall not apply to this contract so far as it may be within the operation or exception of section 116 of the act of Congress approved March 4, 1909 (35 Stats., 1109).
Страница 771 - All claims founded upon the Constitution of the United States or any law of Congress, except for pensions, or upon any regulation of an Executive Department, or upon any contract, express or implied, with the Government of the United States, or for damages liquidated or unliquidated, in cases not sounding in tort, in respect of which claims the party would be entitled to redress against the United States either in a court of law, equity or admiralty if the United States were suable...
Страница 353 - If any part of any deficiency is due to negligence, or intentional disregard of rules and regulations but without intent to defraud. 5 per centum of the total amount of the deficiency (In addition to such deficiency) shall be assessed, collected, and paid in the same manner as if it were a deficiency, except that the provisions of section 571, relating to interest on deficiencies, shall not be applicable.
Страница 577 - No assessment of a deficiency in respect of the tax imposed by this title and no distraint or proceeding in court for its collection shall be made, begun, or prosecuted until such notice...
Страница 704 - In the first sixty days of any year as having been paid from the accumulated profits of the preceding year or years (unless to his satisfaction shown otherwise), and in other respects treating dividends as having been paid from the most recently accumulated gains, profits, or earnings.
Страница 198 - ... unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, a,cts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, or delays of subcontractors or suppliers due to such causes...
Страница 546 - The contractor shall hold and save the Government, its officers, agents, servants and employees, harmless from liability of any nature or kind, Including costs and expenses, for or on account of any patented or unpatented invention, article, or appliance manufactured or used In the performance of this contract, Including their use by th
Страница 704 - States, on or with respect to the accumulated profits of such foreign corporation from which such dividends were paid, which the amount of such dividends bears to the amount of such accumulated profits.