Decisions of the Appeal Section, War Department, Claims Board, Том 7 |
Из књиге
Резултати 1-5 од 100
Страница 18
... accordance with its terms . In May , 1917 , the Quartermaster Corps invited proposals for auto- mobiles , and on June 8 , 1917 , claimant submitted such proposal in writing . This proposal was accepted in writing by the proper officer ...
... accordance with its terms . In May , 1917 , the Quartermaster Corps invited proposals for auto- mobiles , and on June 8 , 1917 , claimant submitted such proposal in writing . This proposal was accepted in writing by the proper officer ...
Страница 78
... accordance with G. O. No. 103 , War Department , 1918 , on a claim for $ 1,333.34 on a formally executed contract . 2. A hearing has been had , at which the claimant was represented . 3. Under date of February 8 , 1919 , the American ...
... accordance with G. O. No. 103 , War Department , 1918 , on a claim for $ 1,333.34 on a formally executed contract . 2. A hearing has been had , at which the claimant was represented . 3. Under date of February 8 , 1919 , the American ...
Страница 79
... accordance with the provisions of the contract and specifications the sum provided as profit thereon under the terms of this contract and not theretofore paid . " ( 2 ) Ten per cent of the cost to the contractor of all materials and ...
... accordance with the provisions of the contract and specifications the sum provided as profit thereon under the terms of this contract and not theretofore paid . " ( 2 ) Ten per cent of the cost to the contractor of all materials and ...
Страница 80
... accordance with this contract and the same is accepted and approved by the Government . " 2. It is strenuously contended that under the language above that only in the event of the plant being erected and installed could the contractor ...
... accordance with this contract and the same is accepted and approved by the Government . " 2. It is strenuously contended that under the language above that only in the event of the plant being erected and installed could the contractor ...
Страница 99
... accordance with existing statutes . The Secretary of War had no authority to adjust such agreements until the act of March 2 , 1919 , became a law . In granting the Secretary of War this special authority to adjust informal agree- ments ...
... accordance with existing statutes . The Secretary of War had no authority to adjust such agreements until the act of March 2 , 1919 , became a law . In granting the Secretary of War this special authority to adjust informal agree- ments ...
Чести термини и фразе
act of March additional affirmed agreed Air Service Claims alleged allowed amount Appeal Section arises Article August authority award Board of Contract Camp cars cent charge Chief of Ordnance CLAIM AND DECISION.-This claimant company constructing quartermaster Contract Adjustment contracting officer cost December decision DECISION.-This claim delivered delivery denying relief Department Claims Board entered evidence expenditures expense facilities filed FINDINGS OF FACT formal contract furnished Government implied agreement installed July June justment labor letter Lieut loss manufacture material MEMORANDUM ment necessary NEWTON D November November 12 obligation October Ordnance Department paid payment Pennsylvania Railroad performance plant pounds prior production purchase order railroad company reason request Secretary Secretary of War September September 25 Service Claims Board settlement Special Adviser statement of claim Steever concurring Storage subcontractor Supply Circular testified tion track trackage tract United War Department Claims War Industries Board wool writing the opinion
Популарни одломци
Страница 836 - States and a reasonable remuneration for expenditures and obligations or liabilities necessarily incurred in performing or preparing to perform...
Страница 361 - Previous and contemporary transactions and facts may be very properly taken into consideration to ascertain the subject-matter of a contract, and the sense in which the parties may have used particular terms...
Страница 934 - ... (a) All labor, material, machinery, hand tools not owned by the workmen, supplies and equipment, necessary for either temporary or permanent use for the benefit of said work ; but this shall not be construed to cover machinery or equipment mentioned in section (c) of this article.
Страница 618 - The Contractor shall take advantage to the extent of its ability of all discounts available, and when unable to take such advantage shall promptly notify the Contracting Officer of its inability and its reasons therefor.
Страница 608 - ... used, though permissive In form, is in fact peremptory. What they are empowered to do for a third person the law requires shall be done. The power Is given not for their benefit, but for his. It is placed with the depositary to meet the demands of right, and to prevent a failure of justice. It is given as a remedy to those entitled to invoke its aid, and who would otherwise be remediless.
Страница 344 - October, 1918, during the emergency arising from the declaration of war with the German Empire and prior to November 12, 1918...
Страница 112 - When parties have deliberately put their engagements into writing, in such terms as import a legal obligation, without any uncertainty as to the object or extent of such engagement, it is conclusively presumed that the whole engagement of the parties, and the extent and manner of their undertaking, was reduced to writing...
Страница 681 - Government regulations for handling the wool clip of 1918 as established by the wool division of said board, pursuant to the Executive order dated December 31, 1918, transferring such work to the...
Страница 970 - The Contractor shall be reimbursed in the manner hereinafter described for such of Its actual net expenditures in the performance of said work as may be approved or ratified by the Contracting Officer...
Страница 699 - Schedule 1 hereto attached, and also all costs theretofore expended and for which payment has not previously been made and all obligations incurred solely for the performance of this contract of which the contractor can not be otherwise relieved. To the above may be added such sums as the Chief of Ordnance may deem necessary to fairly and justly compensate the contractor for work, labor, and service rendered under this contract.