Decisions of the Appeal Section, War Department, Claims Board, Том 7 |
Из књиге
Резултати 1-5 од 99
Страница 2
... letter which included the following : 66 * * * It is herewith understood that complete shipment is to be made within 30 days and that payment will be made upon in- voiced weights only when supported by licensed weighmaster's cer ...
... letter which included the following : 66 * * * It is herewith understood that complete shipment is to be made within 30 days and that payment will be made upon in- voiced weights only when supported by licensed weighmaster's cer ...
Страница 26
... letter from the commanding officer of the camp afore- said dated January 5 , 1918. In said letter the following language is used : " I hereby certify and confirm that you have been authorized by me to have the exclusive right and ...
... letter from the commanding officer of the camp afore- said dated January 5 , 1918. In said letter the following language is used : " I hereby certify and confirm that you have been authorized by me to have the exclusive right and ...
Страница 27
... letter of claimant dated October 5 , 1918 , to Maj . Gen. Duval , United States Army , Jacksonville , Fla . , could be considered as the filing of a claim . This " letter , however , makes no mention whatever of any DECISIONS APPEAL ...
... letter of claimant dated October 5 , 1918 , to Maj . Gen. Duval , United States Army , Jacksonville , Fla . , could be considered as the filing of a claim . This " letter , however , makes no mention whatever of any DECISIONS APPEAL ...
Страница 29
... letter to the claimant : " 1. It is requested that you advise this department as to the earliest date at which you contemplate completion of sample cabinets . We should also like to have drawings in as much detail as possible of these ...
... letter to the claimant : " 1. It is requested that you advise this department as to the earliest date at which you contemplate completion of sample cabinets . We should also like to have drawings in as much detail as possible of these ...
Страница 33
... LETTER - SUGGESTION . - A general letter addressed to various concerns engaged in the production of walnut lumber advising that flitches for gunstocks be cut from logs while cutting airplane propellers is a mere suggestion on the part ...
... LETTER - SUGGESTION . - A general letter addressed to various concerns engaged in the production of walnut lumber advising that flitches for gunstocks be cut from logs while cutting airplane propellers is a mere suggestion on the part ...
Чести термини и фразе
act of March additional affirmed agreed Air Service Claims alleged allowed amount Appeal Section arises Article August authority award Board of Contract Camp cars cent charge Chief of Ordnance CLAIM AND DECISION.-This claimant company constructing quartermaster Contract Adjustment contracting officer cost December decision DECISION.-This claim delivered delivery denying relief Department Claims Board entered evidence expenditures expense facilities filed FINDINGS OF FACT formal contract furnished Government implied agreement installed July June justment labor letter Lieut loss manufacture material MEMORANDUM ment necessary NEWTON D November November 12 obligation October Ordnance Department paid payment Pennsylvania Railroad performance plant pounds prior production purchase order railroad company reason request Secretary Secretary of War September September 25 Service Claims Board settlement Special Adviser statement of claim Steever concurring Storage subcontractor Supply Circular testified tion track trackage tract United War Department Claims War Industries Board wool writing the opinion
Популарни одломци
Страница 836 - States and a reasonable remuneration for expenditures and obligations or liabilities necessarily incurred in performing or preparing to perform...
Страница 361 - Previous and contemporary transactions and facts may be very properly taken into consideration to ascertain the subject-matter of a contract, and the sense in which the parties may have used particular terms...
Страница 934 - ... (a) All labor, material, machinery, hand tools not owned by the workmen, supplies and equipment, necessary for either temporary or permanent use for the benefit of said work ; but this shall not be construed to cover machinery or equipment mentioned in section (c) of this article.
Страница 618 - The Contractor shall take advantage to the extent of its ability of all discounts available, and when unable to take such advantage shall promptly notify the Contracting Officer of its inability and its reasons therefor.
Страница 608 - ... used, though permissive In form, is in fact peremptory. What they are empowered to do for a third person the law requires shall be done. The power Is given not for their benefit, but for his. It is placed with the depositary to meet the demands of right, and to prevent a failure of justice. It is given as a remedy to those entitled to invoke its aid, and who would otherwise be remediless.
Страница 344 - October, 1918, during the emergency arising from the declaration of war with the German Empire and prior to November 12, 1918...
Страница 112 - When parties have deliberately put their engagements into writing, in such terms as import a legal obligation, without any uncertainty as to the object or extent of such engagement, it is conclusively presumed that the whole engagement of the parties, and the extent and manner of their undertaking, was reduced to writing...
Страница 681 - Government regulations for handling the wool clip of 1918 as established by the wool division of said board, pursuant to the Executive order dated December 31, 1918, transferring such work to the...
Страница 970 - The Contractor shall be reimbursed in the manner hereinafter described for such of Its actual net expenditures in the performance of said work as may be approved or ratified by the Contracting Officer...
Страница 699 - Schedule 1 hereto attached, and also all costs theretofore expended and for which payment has not previously been made and all obligations incurred solely for the performance of this contract of which the contractor can not be otherwise relieved. To the above may be added such sums as the Chief of Ordnance may deem necessary to fairly and justly compensate the contractor for work, labor, and service rendered under this contract.